The following is our two-week look ahead:
Note: The road closure on El Camino Real did not happen due to the redesign of the storm drain and scheduling conflicts.
Next week we will continue installing curb, gutter, and sidewalk on Vail Avenue. We will also be working on subgrade and bringing in base course in preparation for paving. There will be large equipment on the road during the day.
The following week we will be installing storm drain on El Camino Real. There will be full road closure during the day from July 6th-July 10th. The detour will be through Ute Valley.
Please be advised, the public should seek alternate route if possible to avoid the construction activities.
For further information please contact Sam Minor.